Wednesday, May 20, 2009

Anggaran Kos Upah Ukur Bagi Kerja Topografi

1) Preparatory of workRM 743.00 per partyday

2) Planimetric control & connection RM 2.00per m

3) Height control RM 464.38 per km

4) Topography surveyRM495.33per ha

5) MonumentingRM185.75per no.

6) Mobilization &DemobilizationRM743.00per partyday

7) Survey of bridge siteRM4086.50per ha

8) Cross sectioningwith sounding

a) Depth of water less than 1 m RM5944.00per km
greater than 1 m

1) Mobilization and demobilizationof boatRM600.00per boat
2) Boat rentalRM300.00per day
3) Cross sectioningRM5944.00per km